SCOPE OF DESIGN AND ENGINEERING


SCOPE OF SUPPLY


Scope of erection & commissioning


Power supply distribution

Un-conditioned power shall be provided at a single point within 5 meter distance from the plc panel. The plc panel should be powered by conditioned ups which is to be supplied and installed by the bidder. Power distribution is in the scope of bidder.


Calibration and commissioning

Individual calibration and commissioning of all erected instruments, control loop commissioning is in the scope of the contractor. The panel instruments shall be calibrated according to the data sheet provided by the purchaser.
Troubleshoot the plc communication (rs 232/422/485, ethernet, usb to serial communication, modbus and etc.. We are giving solution to the software error and corruption and also we are giving guide line to the proper arrangement for your industry.
Programming for industry process like bottle or paint filling, control valves, multilevel car parking, vehicle cleaning process and etc,